CONSTRUCTION

Construction Works for LOT 2 - Sagarejo Bypass from km27+840 to km35+500 of Tbilisi – Bakurtsikhe – Lagodekhi International Road (GOG/CW/RFB-01 Lot 2) .GEORGIABACK
Client:Roads Department of Georgia under the Ministry of Regional Development and Infrastructure of Georgia
Construction year:13/12/2021 - On going
Location:Sagarejo. GEORGIA
 Length of Highway: Total Length of Highway  ( 7,600.00 meter) and Total Length of Access Roads (20,660.00 meter)
Earthworks (Excavation and Backfilling):2,350,000 m³
Wick Drain Works for Soil Improvement :943,000 meter
Stone Column Works for Soil Improvement:44,000 meter
Plant-mix Subbase and Base Course: 288,000 m³
Asphalt  Base - Asphalt Surface Course::70,000 m³
Pile Works ( 1200 mm dia):17,700 m
RC Concrete Works:49,670 m³
Under pass- Over pass -Hydraulic Bridge:3 - 4 -10 Nos. Total Length of Bridges:  627 meter
RC Culverts:54 Nos. Total Length of  Culverts:  1,130 meter
Göçay İnşaat Taahhüt ve Ticaret A.Ş. and Maqro Cons.LLC (Georgia) JV. is constructing  this project . (Share of Maqro and Göçay : %50)