| Client | : | NÖMAYG Joint Venture |
|---|---|---|
| Construction year | : | 27/09/2010 - 31/12/2015 |
| Location | : | Gebze-Orhangazi |
| Length | : | 10.8 Km (2x3 Motorway) |
| Earthworks ( Excavation and Filling Works) | : | 10.593.000 m³ |
| RC Concrete Works | : | 70.000 m3 |
| Pre-fabricated Beam | : | 60.000 Tones |
| Viaduct | : | 2 units |
Göçay - Makyol JV. (%50 -%50) constructed The Project.